A one-gigawatt AI campus draws as much power as a large city and is assembled from copper, steel, concrete and high-voltage equipment. The published figures for its bulk materials vary several-fold; the figures for its electrical equipment show waiting times of two to six years. This Dispatch tests where the build-out of artificial intelligence is constrained, and finds the answer in transformers, switchgear and turbines.
At full load, a campus drawing one gigawatt of electricity would consume about 8.8 terawatt-hours a year, by Titanica’s arithmetic roughly 5 per cent of the 176 terawatt-hours that every data centre in the United States used in 2023, according to the Lawrence Berkeley National Laboratory.1 Several such campuses are under construction. The International Energy Agency (IEA) estimates that a typical AI-focused data centre consumes as much electricity as 100,000 households and that the largest now being built will consume twenty times as much.2 Objects of this size are usually described by what they compute. The documents that permit, finance and supply them describe what they are made of.
Thesis: a gigawatt-scale AI data centre is an industrial object whose binding constraint lies in its electrical equipment (high-voltage transformers, switchgear, gas turbines and grid connections) more than in its bulk materials or its software, so that the expansion of artificial intelligence now advances at the pace of the heavy electrical industry.
Three tests can falsify it, each on public data:
- Bill of materials. Engineering or industry sources give quantities per megawatt for copper, steel, concrete, generators and water. If no reliable figures exist, the Dispatch says so and reports ranges by source.
- Bottlenecks. Lead times and prices for large power transformers, switchgear and gas turbines rose materially between 2024 and 2026 in official or industry data. If lead times are normal, the thesis fails.
- Scale. Data-centre capital spending and construction in 2026 are large relative to other industrial investment. If the comparison is weak, the claim about industrial scale is narrowed.
What a gigawatt contains
No engineering body publishes a standard bill of materials for an AI data centre. The estimates that exist come from consultancies, equipment makers and individual projects, and they measure different things: some count only the building, some the electrical and cooling plant, some a ten-year life cycle with refits. The sustainable data-centre roadmap of the Innovation for Cool Earth Forum (ICEF), published in October 2025, states the problem directly: accurate data on the physical materials going into modern data centres are scarce, and robust estimates for structural steel and rebar are rare.3
Copper illustrates the spread. Bloomberg Intelligence uses an intensity of 27 to 33 tonnes per megawatt, citing a study of Microsoft’s Chicago data centre at 27 tonnes per megawatt and an earlier Schneider Electric estimate of 66 tonnes per megawatt that covered a ten-year life cycle.4 The cost consultancy Linesight, writing in July 2026, gives about 11.6 tonnes per megawatt and attributes more than 80 per cent of a facility’s copper to cooling and electrical systems.5 Scaled to one gigawatt, these figures range from about 11,600 to 66,000 tonnes, a factor of almost six.
Steel and concrete are wider still. The ICEF roadmap models a 200-megawatt reference facility with 50,000 to 75,000 tonnes of structural steel and rebar and 300,000 cubic metres of concrete, within a stated range of 55,000 to 500,000 cubic metres that depends on building code, seismic rules and design; it also reproduces a Schneider Electric figure of about 275 tonnes of steel per megawatt.3 The chief technology officer of Pure Data Centres Group, quoted by Data Centre Magazine, gave 4,000 tonnes of steel for a 30-megawatt data centre, about 133 tonnes per megawatt.6
Backup generation can be read from air permits. Oregon’s Department of Environmental Quality reported in July 2026 that the state’s 39 permitted data-centre campuses held 2,482 large generators with 6,328 megawatts of capacity, an average of about 2.55 megawatts per unit.7 Maryland’s environmental department authorised an Amazon campus in Frederick to install 92 diesel generators of 2,750 kilowatts each, about 253 megawatts, plus smaller units.8 Water depends on the cooling design. Berkeley Lab puts the average direct on-site water use of US data centres at just over 0.36 litres per kilowatt-hour in 2023, rising to 0.45–0.48 by 2028, and estimates the water consumed indirectly at power plants at about 4.52 litres per kilowatt-hour, more than twelve times the direct figure.1
| Item | Per MW, as published | Scaled to 1 GW | Source and scope |
|---|---|---|---|
| Copper | 11.6 t | ≈ 11,600 t | Linesight (2026); installed capacity |
| Copper | 27–33 t | 27,000–33,000 t | Bloomberg Intelligence; Microsoft Chicago study at 27 t |
| Copper | 66 t | ≈ 66,000 t | Schneider Electric via BI; ten-year life cycle |
| Structural steel and rebar | ≈ 133 t | ≈ 133,000 t | Pure Data Centres Group (4,000 t per 30 MW) |
| Structural steel and rebar | 250–375 t | 250,000–375,000 t | ICEF 200 MW reference; Schneider at ≈ 275 t |
| Concrete | 275–2,500 m³ | 0.28–2.5 million m³ | ICEF range; 1,500 m³ per MW assumed |
| Floor area | 300–600 m² | 300,000–600,000 m² | ICEF range for 200 MW facilities |
| Large backup generators | ≈ 0.39 units | ≈ 390 units (illustrative) | Oregon DEQ average unit of 2.55 MW, full backup assumed |
| Heavy-duty gas turbines, if self-supplied | n/a | ≈ 3 units (illustrative) | Wood Mackenzie: 24–30 turbines for a 9.2 GW project |
| Large power transformers | n/a | No public per-GW count found | n/a |
| Electricity at full load | 8,760 MWh/yr | 8.76 TWh/yr | Physical maximum; actual use is lower |
| Direct water, evaporative cooling | 0.36 L/kWh | ≈ 3.2 billion L/yr (illustrative) | LBNL 2023 US average site WUE; closed-loop designs use far less |
The first test therefore returns a partial result. Quantities exist, from credible sources, for copper, steel, concrete, generators and water, and they confirm that a gigawatt campus contains materials on the scale of a heavy industrial plant: at the ICEF reference assumptions, about 1.5 million cubic metres of concrete and up to 375,000 tonnes of steel. The figures do not converge. Copper estimates differ by a factor of almost six, concrete by a factor of nine, and no public source gives a count of high-voltage transformers per gigawatt. The bill of materials can be stated as a set of ranges. It cannot yet be stated as a number.
The equipment with the longest queue
The second test concerns the equipment that converts transmission-voltage electricity into power a server can use, and the turbines that increasingly generate it. Here the data are consistent across sources and over time.
The President’s National Infrastructure Advisory Council reported in June 2024 that a utility or developer ordering a transformer might wait two to four years for delivery, compared with months as recently as 2020, and that one large US plant had disclosed a five-year wait.9 It quoted Wood Mackenzie’s estimate that transformer lead times had risen from about 50 weeks in 2021 to 120 weeks on average in 2024, with large substation and generator step-up units ranging from 80 to 210 weeks, and noted that transformer prices were 80 per cent higher than at the start of the pandemic.9
Wood Mackenzie’s supply-chain survey, published with American Clean Power in September 2025, put average lead times in the second quarter of 2025 at 128 weeks for power transformers and 143 weeks for generator step-up transformers, both slightly lower than in the first quarter, and at about 44 weeks for switchgear.10 The same survey recorded price increases between 2019 and 2025 of about 35 per cent for transformers, 47 per cent for switchgear and 85 per cent for circuit breakers, and demand growth since 2019 of 116 per cent for power transformers and 274 per cent for generator step-up units.10 In July 2026 the firm’s senior analyst Ben Boucher told Reuters that generator step-up lead times had passed 160 weeks by the first quarter of 2026, compared with an average of 143 weeks in 2024, and that high-voltage circuit breakers had reached 125 weeks in the second half of 2025, against 77 weeks in 2023.11 He said that data centres’ share of the US electrical equipment market could rise to 40 per cent under accelerated scenarios, from just under 2 per cent in 2020.11
Gas turbines show the same pattern on a longer clock. In April 2026 Wood Mackenzie reported that global turbine orders stood at 110 gigawatts at the end of 2025 against annual manufacturing capacity of 60 to 70 gigawatts, and projected prices of $600 per kilowatt by the end of 2027, 195 per cent above 2019.12 Its analyst Aurora Tenorio referred to six-year lead times and order books sold through 2027, and identified the casting of single-crystal turbine blades, performed at scale by a handful of suppliers, as the industry’s critical bottleneck.12
The manufacturers’ own filings show the queue. GE Vernova reported that its gas power equipment backlog and slot reservation agreements rose from 116 to 122 gigawatts in the third quarter of 2026 and that it expected at least 130 gigawatts by the end of the year; the equipment backlog of its Electrification segment, whose revenue growth the company attributed partly to switchgear and transformers, reached $42.2 billion, 60 per cent higher than a year earlier.13 On the earnings call on 28 October, chief executive Scott Strazik said, as reported by Utility Dive, that the company was taking reservations for delivery in 2032 and that its demand came roughly 80 per cent from traditional customers and 20 per cent from data centres; he also described a slower pace of new contracts than in the first half of 2026.14 Siemens Energy reported a gas turbine backlog of 69 gigawatts at the end of June 2026.15
The suppliers are expanding. GE Vernova said in July 2026 that it was on track to reach annual gas turbine output of 20 gigawatts in the third quarter of 2026 and 24 gigawatts in 2028, and that it was taking steps to reach 30 gigawatts in 2030.16 Wood Mackenzie counted nearly $1.8 billion of announced transformer manufacturing investment for the North American market since 2023 and projected that, as capacity grows and renewable demand slows, the US shortfall of generator step-up transformers would narrow from more than 700 units in 2025 to about 140 by 2030.10 Its quarterly survey also recorded a ten-week fall in power transformer lead times in the second quarter of 2025.10 The queue is long; on the industry’s own forecasts it is not permanent.
| Equipment | Period | Lead time or price | Source |
|---|---|---|---|
| Transformers ordered by utilities | 2020 | “Months” | NIAC (2024) |
| Transformers, average | 2021 | ≈ 50 weeks | Wood Mackenzie via NIAC |
| Transformers, average (large units) | 2024 | 120 weeks (80–210) | Wood Mackenzie via NIAC |
| Power transformers | Q2 2025 | 128 weeks | Wood Mackenzie / ACP |
| Generator step-up transformers | 2024 → Q1 2026 | 143 → over 160 weeks | Wood Mackenzie via Reuters |
| High-voltage circuit breakers | 2023 → H2 2025 | 77 → 125 weeks | Wood Mackenzie via Reuters |
| Switchgear | Q2 2025 | ≈ 44 weeks | Wood Mackenzie / ACP |
| Heavy-duty gas turbines | 2026 | Six years; books sold through 2027 | Wood Mackenzie (Apr 2026) |
| GE Vernova gas turbines | Oct 2026 | Reservations for 2032 delivery | GE Vernova call via Utility Dive |
| Transformer prices | 2019–2025 | +35% | Wood Mackenzie / ACP |
| Circuit breaker prices | 2019–2025 | +85% | Wood Mackenzie / ACP |
| Gas turbine prices | 2019 → end-2027 | +195%, to $600/kW (forecast) | Wood Mackenzie (Apr 2026) |
The second test passes. Average transformer lead times more than doubled between 2021 and 2024 and remained above two years through 2025; generator step-up units and high-voltage breakers lengthened again into 2026; turbine makers are selling capacity six years ahead at prices close to three times their 2019 level. The same sources also limit the causal claim. Wood Mackenzie attributes the steepest transformer demand growth since 2019 to renewable generation, each project of which needs a step-up unit, and GE Vernova’s chief executive puts data centres at about a fifth of his turbine demand.1014 The shortage of electrical equipment preceded generative AI. Data centres entered a market already in deficit and are now among its fastest-growing buyers.
Who is paying, and how much
The third test begins with the buyers. Platformonomics, which compiles capital expenditure from company filings, counted $155 billion for Amazon, Alphabet, Meta and Microsoft in 2023 and $251 billion in 2024, including finance leases.17 After the third-quarter reports of October 2026, the four companies guided to roughly $720 to $740 billion for calendar 2026, against about $410 billion in 2025, according to a tracker that links each figure to the company release or call: about $220 billion of cash capital expenditure at Amazon, $195 to $205 billion at Alphabet, about $170 billion at Microsoft including finance leases, and $135 to $145 billion at Meta including finance-lease principal.18 Microsoft lowered its calendar-2026 figure from about $175 billion because capacity it planned to rent from third parties arrived late, and it had earlier reduced the figure by reclassifying future data-centre leases after extending their assumed useful life from 15 to 25 years.1819 Alphabet has said that its spending will rise significantly in 2027, and Amazon that it will spend meaningfully more, without giving a number.2021
Oracle, the fifth large builder, forecast in June 2026 capital expenditure of up to $95 billion for its fiscal year 2027, of which about $70 billion is its own spending and $20 to $25 billion is expected to be repaid by customers.22
| Company | 2024 | 2025 | 2026 guidance | 2027 direction |
|---|---|---|---|---|
| Amazon | 83.9 | ≈ 128 | ≈ 220 (cash) | Higher, no figure |
| Alphabet | 52.5 | ≈ 91 | 195–205 | “Increase significantly” |
| Microsoft | 75.6 | ≈ 118 | ≈ 170 (incl. finance leases) | Fiscal 2027 to grow |
| Meta | 39.2 | ≈ 72 | 135–145 (incl. finance-lease principal) | No figure |
| Total | 251 | ≈ 410 | 720–740 | n/a |
Most of this money buys chips and servers. Alphabet’s finance chief said in July that about 60 per cent of its technical infrastructure spending went to servers and 40 per cent to data centres and networking equipment, according to W.Media.23 The IEA reported in November 2025 that global investment in data centres would reach $580 billion that year, exceeding the $540 billion spent on global oil supply.24 In May 2026 it projected oil supply investment below $500 billion for 2026.25
What the construction statistics show
Capital expenditure includes equipment bought anywhere in the world. Census Bureau construction spending measures only structures put in place in the United States, and so offers a narrower and stricter comparison. It excludes servers and racks and much of the electrical gear installed inside the building.26
In September 2026 the seasonally adjusted annual rate of total US construction spending was $2,186.1 billion, 2.7 per cent below a year earlier; private non-residential construction was $790.6 billion; manufacturing construction was $170.2 billion, 17.0 per cent lower than in September 2025; and construction of power facilities was $191.7 billion, 11.1 per cent higher.27 The Census release does not print a data-centre line; the category sits within office construction and is published in the Bureau’s detailed tables. Trade reports of those tables put data-centre construction at an annual rate of $96.5 billion in September, 90.3 per cent higher than a year earlier.2829 Axios, reporting the July figures, cited estimates that construction accounts for roughly 20 per cent of the all-in cost of a data centre.26
| Category | Sep 2026 | Change vs Sep 2025 |
|---|---|---|
| Total construction | 2,186.1 | −2.7% |
| Private non-residential | 790.6 | +2.3% |
| Power (public and private) | 191.7 | +11.1% |
| Manufacturing (public and private) | 170.2 | −17.0% |
| Private office, including data centres | 145.6 | +39.5% |
| Data centres | 96.5 | +90.3% |
| Data centres as share of manufacturing | 57% | n/a |
The third test passes in part. Measured by capital expenditure, the data-centre build is larger than global investment in oil supply, which the IEA expected it to exceed in 2025 and projects to fall below $500 billion in 2026. Measured by structures alone, data-centre construction in the United States is the fastest-growing category of non-residential building but remains smaller than factory construction, at about 57 per cent of it, and smaller than construction of power facilities. The claim that a gigawatt campus is among the largest industrial objects built in series therefore holds for its cost and its electrical load. It does not hold for its building fabric, which by value is the smaller part of the object.
Two campuses, read from their filings
The campus in Abilene, Texas, developed by Crusoe on the Lancium Clean Campus and leased to Oracle and OpenAI according to DatacenterDynamics, shows how the parts are assembled. Crusoe announced in March 2025 a second phase of six buildings, bringing the site to eight buildings, about 4 million square feet and 1.2 gigawatts; the first phase comprised two buildings of 980,000 square feet and more than 200 megawatts.30 The power plan, as described by Crusoe, combines a 1.2-gigawatt grid interconnection with behind-the-meter batteries and solar, natural-gas turbines for backup, and direct-to-chip liquid cooling through a closed loop that Crusoe describes as having zero water evaporation; about 2,000 people worked on the site daily, a number expected to approach 5,000.30 DatacenterDynamics reported that the first two buildings were operating for Oracle Cloud Infrastructure by September 2025 and that the last building had been topped out.31 In March 2026 Crusoe announced an adjacent 900-megawatt campus for Microsoft with its own on-site power plant, which would take the Abilene site to 2.1 gigawatts.32
Meta’s Hyperion campus in Richland Parish, Louisiana, shows the same object from the side of the utility. Louisiana regulators approved in August 2025 Entergy’s plan to build three gas-fired plants for a facility then described as 4 million square feet.33 On 27 March 2026 Entergy Louisiana and Meta announced an agreement for seven further combined-cycle gas plants of more than 5,200 megawatts, about 240 miles of 500-kilovolt transmission lines, battery storage and up to 2,500 megawatts of solar; the seven plants require regulatory approval.34
| Component | Abilene, Texas (Crusoe; Oracle / OpenAI) | Hyperion, Louisiana (Meta; Entergy) |
|---|---|---|
| Stated capacity | 1.2 GW; 2.1 GW with adjacent Microsoft campus | Not verified in sources consulted |
| Buildings | 8; ≈ 4 million sq ft (≈ 310 m² per MW) | ≈ 4 million sq ft (2025 plan) |
| Grid connection | 1.2 GW interconnection | ≈ 240 miles of 500 kV lines (proposed) |
| Generation | Gas turbines for backup; batteries, solar | 3 gas plants approved (2025); 7 more, >5.2 GW, proposed |
| Other supply | Behind-the-meter storage | Up to 2.5 GW solar; battery storage |
| Cooling | Closed-loop direct-to-chip, zero evaporation (stated) | Not disclosed in sources consulted |
| Workforce | ≈ 2,000 daily, rising toward 5,000 (2025) | Not disclosed in sources consulted |
The two campuses describe one pattern. The structures are large but conventional, built in phases of a few hundred megawatts. The items that set the schedule are a transmission interconnection, on-site turbines, batteries and, at Hyperion, an expansion that Entergy’s own announcement presents in the vocabulary of a regional power system: plants, high-voltage lines and storage.
Where the build meets resistance
The constraint is also administrative. Texas’s grid operator, ERCOT, was processing large-load interconnection requests of about 474 gigawatts in August 2026, roughly 90 per cent of them data centres, according to a letter from Governor Greg Abbott directing an audit of the queue, as reported by Utility Dive.35
New York moved first on a statewide pause. Its legislature passed the Responsible Data Center Development Act on 4 June 2026, including a one-year moratorium on permits for data centres of 20 megawatts or more.36 On 14 July Governor Kathy Hochul signed Executive Order 62 instead, which suspends discretionary environmental permitting for new data centres of 50 megawatts or more for up to a year while the state prepares a generic environmental impact statement; the order cites nearly 12 gigawatts of data-centre load in the state grid operator’s interconnection queue.3738 In the most recent reports found for this Dispatch the bill had not been signed, and the governor had until 31 December to act on it; one law firm expected a veto.3937
Some projects have been delayed or withdrawn. In March 2025 analysts at TD Cowen said Microsoft had walked away from projects in the United States and Europe totalling about two gigawatts, which they attributed to oversupply relative to its demand forecast.40 Sightline Climate estimated in 2026 that 30 to 50 per cent of US data-centre projects scheduled for the year would miss their timelines, an estimate that SemiAnalysis disputed in June after reviewing individual filings.4142 Other sites are being adapted from existing buildings: a former Cboe headquarters at 400 South LaSalle Street in Chicago was bought for conversion into a data centre,43 and in August 2026 a developer filed plans to convert part of the 300 West Adams Building, a designated city landmark from the 1920s.44
The strongest counter-argument
A data centre is a building full of computers, and most of its cost lies in the chips. On Alphabet’s account, servers took 60 per cent of its infrastructure spending; construction is estimated at about a fifth of a data centre’s all-in cost; and the equipment shortages predate AI and have causes, from renewables to ageing grids, that would persist without it.232610 On this reading the materials story is a sideshow, and the binding constraint on AI is the supply of advanced chips and the electricity they need, a matter of energy policy more than of heavy industry.
Berkeley Lab also records efficiency gains that cut against the materials story: the average power usage effectiveness of US data centres fell from 1.6 in 2014 to 1.4 in 2023 and is projected at 1.15 to 1.35 by 2028, meaning less cooling and power plant per unit of computing.1
The counter-argument is correct on cost and on causation. Chips dominate the bill, the transformer deficit was visible before generative AI, and data centres account for a minority of turbine demand at the largest manufacturer. It is weaker on timing. On the sources above, a generator step-up transformer now takes more than three years to arrive, a high-voltage breaker more than two, and GE Vernova is reserving turbine slots for 2032. A campus cannot run its chips until its electrical plant is installed, and the electrical plant is the part ordered furthest in advance. The thesis is narrowed accordingly: electrical equipment sets the pace of the build-out, while chips set most of its cost.
A queue measured in megavolt-amperes
The Vulcan Domain reads economies through what things are made of. Read that way, the AI data centre has two bills: one of silicon, which dominates its cost, and one of copper, steel and electrical machinery, which dominates its calendar. The second bill has the longer delivery dates. The companies building the campuses have responded as industrial buyers do when supply is short, by reserving factory slots years in advance, financing power plants and transmission lines, and accepting turbine prices that Wood Mackenzie expects to reach almost three times their 2019 level.
The evidence supports a narrower version of the opening claim. A gigawatt campus is among the largest industrial objects now being built by cost and by electrical load, though not by the value of its buildings, and its completion depends on equipment produced by a small number of manufacturers working through multi-year order books. Whether that constraint eases will be visible in three places: the Census line for data-centre construction, which the Bureau updates on 1 December; Wood Mackenzie’s lead-time surveys; and the fourth-quarter backlogs of the turbine makers, due early next year.
- Arman Shehabi et al., Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report”, LBNL-2001637, December 2024 (official). https://eta-publications.lbl.gov/publications/2024-lbnl-data-center-energy-usage-report ; full text: https://climate.mit.edu/sites/default/files/2025-02/lbnl-2024-united-states-data-center-energy-usage-report.pdf (accessed 9 November 2026) ↩︎
- International Energy Agency, “Energy and AI: Executive summary”, April 2025 (official). https://www.iea.org/reports/energy-and-ai/executive-summary (accessed 9 November 2026) ↩︎
- Julio Friedmann and Colin McCormick, “Embodied Greenhouse Gas Emissions (Scope 3)”, chapter 3.3 of the ICEF Sustainable Data Centers Roadmap, Innovation for Cool Earth Forum, October 2025 (expert report). https://icef.go.jp/wp-content/themes/icef_new/pdf/roadmap/2025/CHAPTER%20%E2%85%A2%20%E2%80%93%203.%20EMBODIED%20GREENHOUSE%20GAS%20EMISSIONS%20(SCOPE%203).pdf (accessed 9 November 2026) ↩︎
- Grant Sporre and Rob Barnett, Bloomberg Intelligence, “Copper demand is set for data-center boost”, undated web edition (analyst estimate). https://www.bloomberg.com/professional/insights/commodities/copper-demand-is-set-for-data-center-boost (accessed 9 November 2026) ↩︎
- Steve Raye, Linesight, “Why copper volatility presents a growing challenge for APAC data centres”, 28 July 2026 (analyst estimate). https://www.linesight.com/insights/copper-volatility-apac-data-centres/ (accessed 9 November 2026) ↩︎
- Data Centre Magazine, July 2025, p. 177, figures attributed to Ian Whitfield, Pure Data Centres Group (press report). https://publication.datacentremagazine.com/data-centre-magazine-july-2025/0945080001751282242/p177 (accessed 9 November 2026) ↩︎
- Oregon Department of Environmental Quality, “Data Center Air Quality Permitting”, presentation, 31 July 2026 (official). https://www.oregon.gov/energy/get-involved/Documents/2026-07-31-Oregon-DEQ-Air-Quality-Permitting-Presentation.pdf (accessed 9 November 2026) ↩︎
- Maryland Department of the Environment, Air and Radiation Administration, “Final Determination Concerning a Permit-to-Construct Application Submitted by Amazon Data Services, Inc. for their Proposed Frederick, Maryland Data Center Campus”, 2026 (official). https://mde.maryland.gov/datacenters/Documents/2026_FinalDeterminationandResponsetoComments.pdf (accessed 9 November 2026) ↩︎
- President’s National Infrastructure Advisory Council, “Addressing the Critical Shortage of Power Transformers to Ensure Reliability of the U.S. Grid”, draft, June 2024 (official). https://cisa.gov/sites/default/files/2024-06/DRAFT_NIAC_Addressing%20the%20Critical%20Shortage%20of%20Power%20Transformers%20to%20Ensure%20Reliability%20of%20the%20U.S.%20Grid_Report_06052024_508c.pdf (accessed 9 November 2026) ↩︎
- Wood Mackenzie in partnership with American Clean Power, “Making the connection: Meeting the electric T&D supply chain challenge”, executive summary, September 2025 (analyst estimate). https://www.powermag.com/wp-content/uploads/2026/01/making-the-connection-executive-summary-september-2025.pdf (accessed 9 November 2026) ↩︎
- Kavya Balaraman, Reuters, “US power companies face long waits for transformers amid data center surge”, 9 July 2026, as republished by ColoradoBiz (press report). https://coloradobiz.com/us-power-companies-transformer-waits-data-center-demand/ (accessed 9 November 2026) ↩︎
- Wood Mackenzie, “Gas turbine prices soar 195% as market faces supply-demand crisis”, news release, 1 April 2026 (analyst estimate). https://www.woodmac.com/press-releases/gas-turbine-prices-soar-195-as-market-faces-supply-demand-crisis/ (accessed 9 November 2026) ↩︎
- GE Vernova Inc., “GE Vernova reports strong third quarter 2026 financial performance”, 28 October 2026, exhibit to Form 8-K (company filing). https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000162/gevpressrelease3q26.htm (accessed 9 November 2026) ↩︎
- Brian Martucci, Utility Dive, “GE Vernova in $9B deal to buy high-voltage manufacturer as gas turbine orders slow”, 29 October 2026 (press report). https://www.utilitydive.com/news/ge-vernova-in-9b-deal-to-buy-high-voltage-manufacturer-as-gas-turbine-orde/873223/ (accessed 9 November 2026) ↩︎
- Mark Jaffe, EUCI, “Natural gas turbine manufacturers see order backlog grow as worldwide demand soars”, 18 August 2026 (press report). https://www.euci.com/?p=190165 (accessed 9 November 2026) ↩︎
- GE Vernova Inc., “GE Vernova reports second quarter 2026 financial results and raises 2026 financial guidance”, 22 July 2026, exhibit to Form 8-K (company filing). https://www.sec.gov/Archives/edgar/data/0001996810/000199681026000147/gevpressrelease2q26.htm (accessed 9 November 2026) ↩︎
- Platformonomics, “Follow the CAPEX: Cloud Table Stakes 2024 Retrospective”, February 2025 (analyst estimate compiled from company filings). https://platformonomics.com/2025/02/follow-the-capex-cloud-table-stakes-2024-retrospective/ (accessed 9 November 2026) ↩︎
- Trace Cohen, Value Add VC, “Big Tech AI Spending Tracker”, updated 4 November 2026 (analyst estimate citing company releases and earnings calls of 21–29 October 2026). https://valueaddvc.com/ai-spending (accessed 9 November 2026) ↩︎
- PYMNTS, “Microsoft Extends Data Center Lifespans to Soften AI Buildout Costs”, July 2026 (press report of Microsoft’s fiscal fourth-quarter 2026 call). https://www.pymnts.com/?p=4019068 (accessed 9 November 2026) ↩︎
- InsiderFinance, “Alphabet Q3 2026 Earnings Highlight AI CapEx”, 29 October 2026 (press report of Alphabet’s third-quarter 2026 results). https://www.insiderfinance.io/news/alphabet-q3-2026-earnings-highlight-ai-capex (accessed 9 November 2026) ↩︎
- Mass Market Retailers, “Amazon misses on third-quarter earnings”, 29 October 2026 (press report of Amazon’s third-quarter 2026 release and call). https://massmarketretailers.com/amazon-misses-on-3q-earnings/ (accessed 9 November 2026) ↩︎
- Reuters via The Standard (Hong Kong), “Oracle’s AI spending blows past estimates, raising worries over growing debt”, 11 June 2026 (press report). https://www.thestandard.com.hk/finance/article/334347/Oracles-AI-spending-blows-past-estimates-raising-worries-over-growing-debt (accessed 9 November 2026) ↩︎
- W.Media, “AI infrastructure demand pushes Alphabet’s 2026 capex guidance to US$ 205 billion”, 23 July 2026 (press report). https://w.media/?p=41917 (accessed 9 November 2026) ↩︎
- RTÉ News, “World oil and gas demand could grow until 2050, IEA says”, 12 November 2025 (press report of the IEA World Energy Outlook 2025). https://www.rte.ie/news/business/2025/1112/1543486-international-energy-agency-outlook (accessed 9 November 2026) ↩︎
- WAM, “Global energy investment projected to reach $3.4 trillion in 2026: IEA”, 28 May 2026 (press report of the IEA World Energy Investment 2026). https://www.wam.ae/en/article/c0fuuxe-global-energy-investment-projected-reach-34 (accessed 9 November 2026) ↩︎
- Axios, “Data center construction spending surged in July”, 1 September 2026 (press report). https://www.axios.com/2026/09/01/ai-data-center-constructon-spending (accessed 9 November 2026) ↩︎
- US Census Bureau, “Monthly Construction Spending, September 2026”, release CB26-176, 2 November 2026 (official). https://www.census.gov/construction/c30/pdf/release.pdf (accessed 9 November 2026) ↩︎
- Electrical Marketing, “September Total Construction Spending Drops -1.9% $2,186.1 Billion, Down -2.9% YOY”, 5 November 2026 (press report of Census data). https://www.electricalmarketing.com/economic-data/construction-industry/article/55417080/september-total-construction-spending-drops-19-21861-billion-down-29-yoy (accessed 9 November 2026) ↩︎
- Wolf Richter, Wolf Street, “No Inflection Point Yet: Near-Exponential Data Center Boom Sends Shockwaves to Industrial Economy”, 2 November 2026 (commentary on Census data). https://wolfstreet.com/2026/11/02/no-inflection-point-yet-near-exponential-data-center-boom-sends-shockwaves-to-industrial-economy-construction-hit-by-2nd-wave-of-inflation/ (accessed 9 November 2026) ↩︎
- Crusoe, “Crusoe expands AI data center campus in Abilene to 1.2 gigawatts”, 18 March 2025 (company release). https://www.crusoe.ai/resources/newsroom/crusoe-expands-ai-data-center-campus-in-abilene-to-1-2-gigawatts (accessed 9 November 2026) ↩︎
- DatacenterDynamics, “Crusoe tops out final building at OpenAI Stargate data center campus in Abilene, Texas”, 2026 (press report). https://datacenterdynamics.com/en/news/crusoe-tops-out-final-building-at-openai-stargate-data-center-campus-in-abilene-texas (accessed 9 November 2026) ↩︎
- Crusoe, “Crusoe announces new 900 MW AI factory campus in Abilene, Texas to support Microsoft AI infrastructure”, 27 March 2026 (company release). https://www.crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure (accessed 9 November 2026) ↩︎
- Josh Saul and Riley Griffin, Bloomberg, “Entergy to Build Three Gas Plants for Meta’s Biggest Data Center”, published by Insurance Journal, 21 August 2025 (press report). https://www.insurancejournal.com/news/southcentral/2025/08/21/836573.htm (accessed 9 November 2026) ↩︎
- Shreveport-Bossier Journal, “Entergy Louisiana, Meta announce massive expansion agreement — seven new power plants, $2.65 billion in customer savings”, 30 March 2026 (press report of the Entergy Louisiana announcement). https://shreveportbossierjournal.com/2026/03/30/entergy-louisiana-meta-announce-massive-expansion-agreement-seven-new-power-plants-2-65-billion-in-customer-savings/ (accessed 9 November 2026) ↩︎
- Utility Dive, report on Governor Abbott’s directive to audit data centres in the ERCOT interconnection queue, August 2026 (press report). https://utilitydive.com/news/ercot-texas-puc-data-center-audit/828472 (accessed 9 November 2026) ↩︎
- Mintz, “New York Legislature Passes First-in-the-Nation Data Center Moratorium, Awaiting Governor’s Signature”, 12 June 2026 (commentary). https://www.mintz.com/insights-center/viewpoints/55076/2026-06-12-new-york-legislature-passes-first-nation-data-center (accessed 9 November 2026) ↩︎
- Hodgson Russ, “Governor Hochul Signs First Statewide Data Center Moratorium in the U.S.”, July 2026 (commentary). https://www.hodgsonruss.com/newsroom/alerts/governor-hochul-signs-first-statewide-data-center-moratorium-in-the-u-s (accessed 9 November 2026) ↩︎
- Davis Polk, “New York State enacts data center moratorium”, 23 July 2026 (commentary). https://www.davispolk.com/insights/client-update/new-york-state-enacts-data-center-moratorium (accessed 9 November 2026) ↩︎
- The Ithaca Voice, “Pressure mounts for Kathy Hochul to sign data center moratorium bill”, August 2026 (press report). https://ithacavoice.org/2026/08/pressure-mounts-for-kathy-hochul-to-sign-data-center-moratorium-bill/ (accessed 9 November 2026) ↩︎
- The Edge Malaysia, “Microsoft abandoned data centre projects — analysts”, 27 March 2025 (press report citing TD Cowen). https://theedgemalaysia.com/node/749541 (accessed 9 November 2026) ↩︎
- GadgetReview, “Half of Planned US Data Center Builds Face Delays or Cancellations”, 2026 (press report citing Sightline Climate). https://www.gadgetreview.com/?p=368179 (accessed 9 November 2026) ↩︎
- SemiAnalysis, “Stop Saying Half of 2026 US Datacenter Capacity Is Canceled”, 18 June 2026 (analyst commentary). https://newsletter.semianalysis.com/p/stop-saying-half-of-2026-us-datacenter (accessed 9 November 2026) ↩︎
- DatacenterDynamics, “Legacy Investing buys Chicago office set to be turned into data center”, 2025 (press report). https://www.datacenterdynamics.com/en/news/legacy-investing-buys-chicago-office-set-to-be-turned-into-data-center/ (accessed 9 November 2026) ↩︎
- DatacenterDynamics, “12-story office building in Chicago, Illinois eyed for data center conversion”, August 2026 (press report). https://www.datacenterdynamics.com/en/news/12-story-office-building-in-chicago-illinios-eyed-for-data-center-conversion/ (accessed 9 November 2026) ↩︎
- Context
- US data centres used 176 TWh in 2023 (LBNL); the four largest cloud companies guide to $720–740bn of 2026 capital spending, and US data-centre construction reached a $96.5bn annual rate in September 2026.
- Causes
- Demand for AI computing meets an electrical-equipment market already in deficit since 2020, with transformer, breaker and turbine lead times of two to six years and prices well above 2019.
- Actors
- Amazon, Alphabet, Microsoft, Meta and Oracle as buyers; GE Vernova, Siemens Energy and transformer makers as suppliers; Crusoe, Meta and Entergy at two named campuses; ERCOT and New York State as regulators; Wood Mackenzie, LBNL, the IEA and the Census Bureau as measurers.
- Perspectives
- Three tests (bill of materials, bottlenecks, scale) are applied and reported as partial, passed and partially passed; the counter-argument that chips and energy dominate is stated and accepted on cost and causation.
- Relationships
- Opens the Vulcan Domain. Related: Kinesis, Why Planes Fly No Faster Than in 1970; Anthropocene, The 1.5 Degrees and the Overshoot Without Terms.